2435 Haste Street, Berkeley CA 94704
Eight Story, 37-unit apartment building with amenity space.
General Construction Schedule
Construction Activities
Major phases of construction include to following:
Demo of existing building and site hardscape
Excavation and grading
Underground utilities
Relocation of fire hydrant
Form and pour concrete for foundation and 2 concrete podium levels
Five stories of vertical wood framing including exterior and interior finishes
Site improvements include landscaping, new sidewalk, etc.
Daily construction activities: expect the use of hand tools(hammers, drills, etc.) Hauling and hoisting of material. General
construction equipment that will be in use at various times during construction will include bobcats, backhoes, lift equipment,
mobile crane and a variety of other equipment which will be added to this site as site logistics are completed.
Anticipated General Schedule
Construction/demo start: September 2025
Completion: May/June 2027
Daily Construction Schedule
Work will commence 7am - 6pm Monday through Friday
Project is approved for Saturday work 9am - 4pm, no work on Sunday
Noise Management Contact
Name/Phone/Email will be provided at the start of demolition or any construction activity